Professional Experience

2008 – Date :: Systech Group Limited/Systech Dispute Services Limited (UK)

Divisional Director – Dispute Services

  • Provision of specialist dispute resolution services in connection with construction and engineering projects both in the United Kingdom and internationally.
  • Provision of contractual advice as to the basis and likely success of claims.
  • Preparation and negotiation of claims, counterclaims and defence against submitted claims.
  • Professional and technical support in litigation, arbitration and adjudication proceedings.
  • Acting as Expert Witness, particularly on programme matters.
  • Acting as Arbitrator or Adjudicator.
  • Assistance with ‘Due Diligence’ investigations in mergers and acquisitions.

Professional History

  • Testimony experience as Expert Witness on programme matters in an international ICC arbitration concerning the termination of a roadbuilding contract in Bulgaria.
  • Appointed to co-ordinate the claims team on a nuclear waste treatment plant and draft claims and pleadings as required.
  • Provided initial strategic advice on programme, contract and quantum in relation to a 227km railway upgrade project in the UK.  Presently awaiting formal Expert appointment.
  • Providing strategic advice and direction to the claims team preparing a disruption and acceleration claim on a railway upgrade project (the provision of a third rail track where existing OCS and drainage systems were in place).
  • Acted on behalf of the Administrators of a temporary works and staging contractor to realise outstanding debts on UK and International projects, including setting strategy for disputed works (including mediation).
  • Prepared an expert report in relation to rebuttal of a delay claim on a new build office and workshop development in adjudication proceedings.  Gave evidence to the tribunal.
  • Lead Expert and strategist on the preparation of pleadings in a major ICC International Arbitration on a railway infrastructure upgrade project with a contract value of €815M in Istanbul. The contract was the FIDIC “Silver Book” (Conditions of Contract for EPC (Engineering, Procurement, Construction) / Turnkey Projects).  Following substantial delays the project was terminated and Systech was appointed by lawyers to produce the final account and claims in preparation for Arbitration.
  • Provided expert advice and strategy for a dispute concerning a major upgrade of Kings Cross station in London: a complex project involving the refurbishment of a major rail terminus whilst remaining fully operational.  The project utilises solar and other technologies not usually associated with a UK rail terminal.  Advice and strategy was given concerning the complex claim involving numerous sectional completion dates and the forensic analysis of a programme with circa 7000 activities.
  • Led a team preparing for adjudication proceedings concerning a major final account for housing stock regeneration and acted as party representative at hearings.
  • Led a team in a series of adjudication proceedings against a local authority on a new build and refurbishment school project.
  • Oversaw the preparation of a delay and disruption claim for a major contractor on a light railway/tramway project in Edinburgh, including the provision of strategic advice.
  • Led a large team preparing delay and loss and expense claims on a €100M highway and tram interface project in Ireland for the joint venture contractors.
  • Prepared an expert report in relation to rebuttal of a delay claim on a new build student accommodation project.
  • Led a team supporting the delay expert in adjudication proceedings with a significant claim and counterclaim concerning an M&E sub-contractor’s time and cost impact on the main contractor’s one year overrun on a mixed use development in London.
  • Led a team and oversaw the preparation of a time impact analysis to support a loss and expense claim on a mixed-use residential/office/retail town centre redevelopment in Berkshire.
  • Appointed as Expert Witness on programme matters in a litigation concerning remedial works leading to a one year delay on a new-build office development in Bristol.
  • Oversaw the preparation of a delay and disruption claim for a major contractor on a tramway project in Edinburgh, including the provision of strategic advice. Led a large team preparing delay and loss and expense claims on a €100M highway and tram interface project in Ireland for the joint venture contractors. Led a team dealing with extension of time issues for a contractor where a design and build office and residential project in Birmingham was overrunning by 18 months, including two adjudications to recover liquidated damages from the contractor.
  • Prepared a loss and expense claim following three sets of adjudication proceedings on a high class residential development in London for the fit-out contractor.
  • Led a team dealing with a £7M claim and £11M counterclaim concerning an M&E sub-contractor’s final account and delay/loss and expense claim on a flagship mixed use development in Central London.
  • Appointed by a national construction firm to provide pre-dispute advice concerning the variation account, extension of time claim, loss and expense claim, contra-account and damages deductions as well as overseeing the progress and completion of a £12 Million mechanical & electrical services sub-contract on a design and build feature office and retail development in central London.  Produced Expert reports and assisted with adjudication proceedings between the employer and main contractor.

1993 – 2008 :: Morris Associates/Morris Associates Limited (Norfolk)

Principal/Director

  • Provision of specialist commercial and contractual services in connection with construction and engineering projects both in the United Kingdom and internationally.
  • Provision of contractual advice as to the basis and likely success of claims.
  • Preparation and negotiation of claims, counterclaims and defence against submitted claims.
  • Professional and technical support in litigation, arbitration and adjudication proceedings.
  • Acting as Expert Witness, particularly on programme matters.
  • Acting as Arbitrator or Adjudicator.
  • Assistance with ‘Due Diligence’ investigations in mergers and acquisitions.

Professional History

  • Appointed by a large regional contractor to give advice on dealing with potential overlapping and concurrent delays on the same project involving interlinked trade sub-contractors.
  • Appointed by a major International engineering company to prepare a time impact analysis on an underground railway upgrade project.
  • Proposed as the adjudicator on a major civil engineering project in Uzbekistan.
  • Appointed as Expert Witness to provide programme advice in relation to a litigation matter concerning bathroom and shower pods on a hotel development.
  • Appointed as advisor to handle a claim and to advise on legal and adjudication matters in relation to a mechanical and electrical services sub-contract.
  • Appointed as Expert Witness to provide programme advice in relation to an arbitration concerning a major town centre supermarket and highways project where the project was completed on time but significantly disrupted.
  • Appointed as Expert Witness to provide programme advice in relation to an arbitration concerning a small office development.
  • Appointed as Expert Witness to provide programme advice in relation to a litigation matter where a contractor is suing an architect for delays (relating back to an arbitration a few years before).
  • Provided independent programme advice to a major UK contractor in relation to a litigation matter where experts have already been appointed for both sides.
  • Provided independent advice to a National Health Service Trust in relation to potential adjudication proceedings from a main contractor for a new-build ward block.
  • Provided advice on possible adjudication proceedings in relation to non-payment of interim applications for a sub-contractor.
  • Appointed as the Expert Witness on programme matters in an arbitration in relation to a structural steelwork sub-contract.
  • Appointed as Expert Witness on programme matters in an arbitration in relation to an infrastructure project in the Falkland Islands.
  • Provided a series of independent reports in relation to multiple adjudication referrals to the Contractor as to the extension of time entitlements of a major concrete structure sub-contractor on a £4½M sub-contract.
  • Provided advice in relation to threatened adjudication proceedings on two flooring sub-contracts to the Contractor.
  • Proposed as member of a three-man adjudicator panel for a three year bridge and roadbuilding project in Bangladesh.
  • Provided independent advice to a National Health Service Trust on the extension of time entitlements of a main contractor for a series of new build ward blocks. Appointed as the Expert Witness on programme matters for any subsequent proceedings.
  • Retained through a main contractor Client to provide advice and completion programmes to a National Health Service Trust on the true progress and projected completion dates of a series of new build ward blocks. The entire appointment was completed within eight days during which time over 400 progress photographs were taken and a fully-detailed completion programme produced.
  • Retained by a major regional contractor to monitor the progress of the substructure and superstructure sub-contractor’s work on a landmark construction project and to assess and agree the latter’s extension of time entitlements.
  • Successfully case-managed an adjudication for a Sub-Contractor, managing the appointment of an adjudicator to decide upon matters in dispute on a services sub-contract. This led to a quick negotiated settlement with the Main Contractor.
  • Prepared the programme aspects of a preliminary report in an arbitration on a major tunnelling and civil engineering project in Hong Kong for the Employer.
  • Acted as Expert Witness on programme matters for a multinational corporation in a litigation matter. The dispute concerned delays by a ceiling sub-contractor and the extent to which any delays had delayed completion of the main contract works.
  • Acted as Expert Witness on programme matters for a curtain walling subcontractor in a litigation matter. The positive case to be considered was the delay and disruption caused by a number of factors. The negative case to be considered was whether the sub-contractor had delayed the main contractor and the extent to which any such delay had delayed completion of the main contract works.
  • Assisted an Expert Witness on quantum to value the amount in dispute on an open cast mining project over ten years.
  • Acted as Expert Witness on programme matters for a developer in an arbitration on a civil engineering project being carried out under an ICE 6th Edition Contract. The matters to be addressed were the defence and counterclaim, specifically the assessment of the original contract period and the time within which the contractor ought to have finished the Works.
  • Prepared advice for a contractor on an inner-city residential block of flat refurbishment project concerning design liability and variation entitlements.
  • Acted as Expert Witness on programme matters for a curtain-walling contractor in a litigation matter. The matters to be addressed were the defence and counterclaim, specifically a delay and disruption claim made against the curtain-walling contractor. The instructions included providing advice upon whether to include a potential claim for extension of time within the pleadings.
  • Prepared a contractual defence for one of a group of Contracting companies once they had determined their employment under the ACA Form of Sub-Contract on two projects, including the preparation of an extension of time claim.
  • Assisted one of a group of Contractors involved in a consultation exercise with a major national retailer by producing a series of programmes on a selection of typical superstore refits to establish model programmes for their store refurbishment partnering strategy.
  • Prepared an extension of time claim during the course of a high-quality refurbishment project including a base programme supported by a dynamic critical path network and its constraint to demonstrate the effects of the delays and disruption incurred.
  • Assisted the Quantum Expert Witness in a professional negligence litigation matter between a Contractor and a Consulting Engineer by producing a series of programmes to reflect the tender position and a delay impact analysis programme to show the effects of a the Engineer’s negligence.
  • Assisted the Quantum Expert Witness in an arbitration under the IFC84 form of contract by producing a series of programmes to reflect the tender position, the as-installed work and a delay impact analysis programme to show the effects of a series of delays.
  • Established base programmes for a major mechanical and electrical services new-build project from the Contractor’s drawn barcharts including dynamic critical path networks.
  • Prepared extension of time claims during the course of a high-quality refurbishment project including establishing a base programme supported by a dynamic critical path network and its constraint to demonstrate the effects of the delays and disruption incurred.
  • Investigated claims situations on three projects for a newly acquired facilities management company.
  • Prepared and agreed extension of time and loss and expense claims on each phase of a hospital refurbishment project for a major national mechanical and electrical services subcontractor including constrained programmes to demonstrate the effects of the delays and disruption incurred.
  • Assisted an international manufacturer of sub-sea oil and gas valves to defend a claim against them for late delivery and subsequent termination of their contract.
  • Prepared a series of programmes for a submitted claim in litigation proceedings on a large urban civil engineering (roadbuilding) project for individual heads of claim.
  • Prepared an extension of time and loss and expense claim for an Italian contractor on a highway contract in Bulgaria.
  • Acted as Expert Witness on Programme Matters in two litigation matters concerning housing association and local authority housing projects.
  • Prepared Further and Better Particulars of a submitted claim in litigation proceedings on a multimillion-pound housing refurbishment scheme for the Plaintiff Contractor, including assessing the programme implications of the events complained of.
  • Prepared three loss and expense claims for a national contractor on related refurbishment projects.
  • Prepared six other extension of time and loss and expense claims for the same contractor on a variety of new-build and refurbishment projects including establishing base programmes supported by dynamic critical path networks and their constraint to demonstrate the effects of the delays and disruption incurred.
  • Assisted an international manufacturer of sub-sea oil and gas valves to defend a claim against them for late delivery.
  • Assisted one of the main insolvency practitioners in their investigations into a building company and realised its outstanding debtor balances upon their appointment as Administrative Receivers.

1991 – 1993 Trett Consulting (Norwich)

Senior Consultant

  • Prepared financial and time impact data analyses of the electrical/software element of a £24M claim on a major civil and process engineering project within the construction of a new steel beam rolling mill.
  • Prepared extension of time claims for three contractors and reported upon the validity of submitted claims on a gas receiving installation to the major valve supplier.

1988 – 1991 J. A. Elliott Limited (Bishop’s Stortford)

Commercial Manager

  • Dealt with litigation, arbitration and claims both for and against the entire Elliott Group of Companies although nominally employed by the major contracting arm of the Group.
  • Negotiated contractual terms for projects with clients as well as professional appointments for design and build contracts with external consultants.
  • Upon the Receivership of the holding company and all but one of the contracting companies, was actively involved in an attempted MBO. Subsequently invited to join J. Jarvis & Sons plc as Area Surveyor reporting at Board level.

1988 – 1988 Wimpey Construction Management (London)

Senior Quantity Surveyor

  • Site-based on the HMP Belmarsh (Woolwich Urban Prison) project responsible for £17M (1988 prices) of M&E services, gates and doors, prison officers’ housing, social club and commissioning packages.
  • Liaised with and directed externally appointed Architects, Engineers and Quantity Surveyors.

1987 – 1987 Bovis Construction (Harrow)

Manager (Surveying) – “I” Division

  • Site-based on the Langham Hilton International development in London responsible for £11M (1987 prices) of new-build offices and refurbished listed offices forming part of the development.
  • Provided value engineering advice to and liaised with the Client and his Architects and Quantity Surveyors.

1980 – 1987 Drake & Scull Engineering Ltd. (Bury St. Edmunds)

Department Surveyor

  • Responsible for all Quantity Surveying functions for the mechanical and latterly the electrical departments of a regional office. The turnover of the electrical department was £1.2M (1987 prices) spread over up to ten projects at a given time. During 1986 was responsible for £1.75M of mechanical services on a hospital project.

Additional Professional Activities

  • Member of the Board of Trustees of the Chartered Institute of Arbitrators
  • Past Chairman of the East Anglia Branch of the Chartered Institute of Arbitrators
  • Former Member of the Arbitration Committee of the Chartered Institute of Arbitrators
  • Member of the East of England Branch Committee of the Association for Project Management
  • Assisted the Department of Trade and Industry during the consultation phase of the drafting of the Arbitration Act 1996
  • Former Member of the British Chambers of Commerce Company Law Consultative Committee
  • Committee member and co-founder of adjudication.co.uk
  • Member of the Society of Construction Law
  • Also runs Web Designers, an Internet Design Consultancy specialising in designing, hosting and maintaining Internet web sites for construction industry, legal and SME clients.

Additional Personal Activities

  • Former High School Governor (2004-2008)
  • Norfolk Youth Football Combination Youth Football Coach (and qualified FA Coach)
  • Administrator, ZRX Owners Club
  • Officer of the Motorcycle Folly (track day organisers)
  • Photography